Construction
The construction began
as soon as the snow melted, at the end of April 2007. The excavation and concrete
work were completed in two weeks. Next, I spent a few days welding and painting
the support columns. The floor system was built in one week and then I spent
a couple of days milling the wall packages. With the help of two additional
men and a construction lift, all of the walls were up within one week. The
roof took two weeks to frame, insulate, trim, and dry in with Ice & Water
Shield. In mid-July, the construction rate slowed down while we waited for
the subcontractors to finish their work and for materials to arrive. By the
end of August, the exterior was complete, the windows were in, and the metal
roof was on. During September, the electrical system, radiant hydronic heating
system, and concrete slab were finished. The interior was drywalled during
October. Interior finishing, trim carpentry, and painting began in November
and my Folks moved in just before Christmas. The entire construction process
took just under 8 months.